Wreck Removal Support for Fedra and New Flame - Gibraltar (2009)



Scope of Work:
- Assist Titan Maritime in the removal of wreck from the seabed of Gibraltar Bay
- Diving in confined spaces through a pipe to the main engine room to secure tanks prior to wreck removal
- Underwater cutting of vessel shell plating for easy removal of wreck
Resources:
- A team of 6 mixed gas divers
- DSV Sirena Real as dive platform and support vessel
- DDC
Five Crane Jib Repairs - Alegeciràs (2008-2009)



Scope of Work:
- Disconnection of crane jib, wires and pins
- Repair and fabricate jib sections
- Restore, fabricate and install damaged crane cabin
Resources:
- Team of 20 workers, including certified welding and cutting team of 12 persons, 6 mechanics and fitters and 2 electricians
- Scaffolding
- 250 - 60 ton crane support
- 685 - 750 m³ of scaffolding
Turn Key Project - Repair of Cable Layer Stinger - Algeciràs (2007)



Scope of Work:
- Repair of stinger sections
- Repair of stinger roller boxes
- Provide procurement system to assist client in repair work
- Provide daily project management reporting system
Resources:
- Team of 178 people including 50 certified welders, 120 fitters, 13 helpers, 16 painters and 4 electricians in 2 shifts of 12 hours
- 1 flat top barge (Viking)
- 9568 m³ of scaffolding for support of stinger